Out-of-cycle assessment of ASX Clear Pty Ltd and ASX Settlement Pty Ltd: Operational Risk Standard – March 2025 2. Assessment
Summary
The incident has revealed serious issues of concern regarding ASXs resourcing and contingency arrangements for current CHESS. Both warrant immediate attention given the potential for delayed settlement to create liquidity stress among participants and undermine confidence in the financial system. The incident occurred against the backdrop of other operational risks the RBA has highlighted over recent assessments. This is consistent with a rating of not observed for the Operational Risk standard.
Resourcing
The FSS require ASX to ensure it can reliably access and utilise well-trained and competent personnel, as well as technical and other resources. These arrangements should be designed to ensure that all key systems are operated securely and reliably in all circumstances. The incident has raised concerns about the level and capacity of ASXs resourcing for the maintenance and support of CHESS.
During the incident, ASX only had one core engineering team working on the issue and progressing towards a solution. There was no capacity to replace members of the core engineering team during breaks. On the morning of Saturday, 21 December, investigation of the root cause was paused for a four-hour period while the core engineering team took a break. As a result, the RBA observed limited progress on identification or resolution throughout most of 21 December. ASXs core engineering team was unable to solve the issue after more than 24 hours. Twenty-eight hours after the incident was first detected, ASX sought additional external resources. The appropriate relevant third-party specialist engineer was unavailable until the following morning, approximately 41 hours after the incident was detected. This specialist engineer ultimately helped identify the root cause and resolve the issue. External support should have been sought more promptly.
- By 30 April, ASX should:
- outline to the regulators how it plans to strengthen its resourcing and third-party support arrangements considering the 20 December 2024 CHESS batch settlement failure incident and ASXs existing obligations and commitment to the public and regulators. This should include an analysis of how the strengthened arrangements will be designed to ensure that all key systems are operated securely and reliably in all circumstances. It will include details on the level and capabilities of the resources that will support the CHESS system.
- communicate publicly its high-level plans for improving the levels of resources and capabilities to support the ongoing operation, maintenance and investment in the current CHESS.
- ASX should implement its plans to strengthen its resourcing and third-party support arrangements on a timeline agreed with the RBA.
Contingency arrangements
Under the FSS, ASX must have a business continuity plan designed to ensure that critical information technology systems can resume operations within two hours following disruptive events and that settlement is completed by the end of the day of the disruption.
The incident revealed that ASX does not have recognised and tested contingency arrangements in place for failure at each step of the CHESS batch settlement process. Contingency arrangements exist only in respect of a failure at the point of submission of the batch into the Reserve Bank Information and Transfer System (RITS); this is only one stage in a multi-stage process. These contingency arrangements were developed by the RBA and are used as contingency arrangements for some other systems that settle through RITS. While ASX was ultimately able to reschedule the batch to the next business day, this was not a procedure that had been regularly tested with, and communicated to, participants.
- By 30 April 2025, ASX should outline option(s) and its plans for implementing contingency arrangements for the current CHESS. The option(s) should ensure there are contingency arrangements that are designed to enable settlement to be completed by the end of the day in the event of failure of any of the seven steps of the batch settlement process outlined in CHESS Batch Settlement Operational Overview.4
- ASX should implement contingency arrangements for the current CHESS on a timeline agreed with the RBA.
Endnotes
Available at: CHESS Batch Settlement Operational Overview. 4